MG ZS EV charging time & cost
to 80% in about 60 minutes on a 50 kW CCS charger (manufacturer claim). Here's how long the MG ZS EV takes on 30–240 kW DC fast chargers, what a charge costs and where to charge it.
Find a fast chargerMG ZS EV battery & charging specs
Manufacturer figures. Range cycles differ between brands, so compare like with like.
| Version | Battery | Max DC power | Official DC charging claim | AC charging | Range |
|---|---|---|---|---|---|
| 50.3 kWh | 50.3 kWh | 50 kW | to 80% in about 60 minutes on a 50 kW CCS charger | 7.4 kW — 8.5–9 h (0–100%) | 461 km (certified) |
Charging the MG ZS EV on Relux chargers
Estimated 10–80% time by charger power, and cost at the indicative ₹18/kWh tariff. Estimates assume the car averages about 80% of the lower of the charger's and the car's peak power; real times vary with battery temperature and state of charge.
| Version | 30 kW DC | 60 kW DC | 120 kW DC | 240 kW DC | Cost 10–80% |
|---|---|---|---|---|---|
| 50.3 kWh | ~88 min | ~53 min | ~53 min | ~53 min | ₹634 |
At Autocar India's tested 6.7 km/kWh, the 50.3 kWh MG ZS EV costs about ₹2.69 per km on a Relux fast charger.
Frequently asked questions
How long does the MG ZS EV take to charge on a fast charger?
MG quotes 50.3 kWh: to 80% in about 60 minutes on a 50 kW CCS charger. On a 60 kW Relux DC charger, expect roughly 53 minutes for 10–80% on the 50.3 kWh version (estimate).
How much does it cost to charge the MG ZS EV at a public fast charger?
At an indicative ₹18 per kWh: 50.3 kWh: about ₹634 for 10–80% (35.2 kWh). The exact tariff for each station is shown in the Relux Electric app before you start.
Can I charge the MG ZS EV at Relux Electric stations?
Yes. The MG ZS EV uses CCS2 (DC), Type 2 (AC). Relux DC fast chargers have CCS2 connectors, and some locations also have Type 2 AC chargers.
What is the battery size and range of the MG ZS EV?
50.3 kWh: 50.3 kWh, 461 km (certified).
Will a 120 kW or 240 kW charger charge the MG ZS EV faster than 60 kW?
Only up to the car's own limit. The MG ZS EV accepts up to 50 kW (50.3 kWh), so a more powerful charger helps only until that peak is reached.